NEW PRODUCTION / WAREHOUSE AND OFFICES 2016

Delivery of the Refrigeration Units New Refrigeration Units to provide all refrigeration. The reclaimed hot water will be used for the new Cellar Door planned for 2018 The roof of the new building is built on the ground, including all electrical and refrigeration plumbing Cranes are on-site, and the roof is being prepared to be lifted Roof is lifted, and the "legs" fold into place - unbelievable! Roof is up, "legs" are down and bolted. All in a couple of hours! Shed is up, shows how much smaller the old factory is. The old factory will eventually be used for bottling and distribution. Concrete Panels are installed for Fire Protection Another larger concrete panel skillfully moved into position Glenn at work in the cherry picker, finishing off the Glycol pipe work All complete and 120 pallets in ... with room ... for the moment!